Excavating work and installation of 150,000 ton surcharge within a compressed (six-week) field schedule. |
Roadwork upgrade consisting of widening of existing, waterline installation (9,500 LF) and asphalt paving (21,000 tons) |
Roadwork upgrade consisting of widening (placed 275,000 yards of material) and asphalt paving (placed 8,500 tons). |
Roadwork upgrade consisting of widening, cement treatment and asphalt paving |